Local view for "http://purl.org/linkedpolitics/eu/plenary/2010-05-18-Speech-2-032"
Predicate | Value (sorted: default) |
---|---|
rdf:type | |
dcterms:Date | |
dcterms:Is Part Of | |
dcterms:Language | |
lpv:document identification number |
"en.20100518.6.2-032"2
|
lpv:hasSubsequent | |
lpv:speaker | |
lpv:spokenAs | |
lpv:translated text |
"Madam President, Commissioner, ladies and gentlemen, I would like to start by reminding you that Parliament has already criticised the enormous delays in implementing the second generation Schengen Information System (SIS II). On 22 October 2009, we adopted a resolution on the SIS II and the Visa Information System. The European Parliament once again expressed deep concern at the delays in commencing operations and requested information from the Commission and the Council on the results of the technical tests, demanding full transparency regarding the implementation process for the SIS II.
The SIS II should have become operational in 2007. We are now in 2010 and no one is able to give a firm answer on when it will be concluded. As regards the package of proposals that we are considering, four fundamental questions arise. First, when is this migration to take place? Before the SIS II can become operational it must be personally tested to check whether the system is capable of functioning in accordance with the technical and operational requirements set out in the respective legal instruments. Only after all these tests have been successfully concluded can migration from the first generation Schengen Information System to the SIS II take place.
Second, have these tests been concluded? No. Faced with enormous delays to the project, and because of all the problems and difficulties encountered, the Council decided to carry out two ‘milestone’ tests: the first in the fourth quarter of 2009 and the second in summer 2010. However, the first test had to be postponed until late January because the prerequisites had not been met. The test took place between 21 and 24 January 2010: apparently the system worked for the first 25 hours, but was notoriously unstable throughout the rest of the test. This test was carried out again between 2 and 5 March, and the final assessment and validation of the second set of tests took place on 6 April.
Although the test conditions were not fully respected by the Member States or the contracted company, and despite the fact that the limited number of transfers did not comply with the required response times, the great majority of Member States concluded that the deviations were insignificant and that the tests’ major objectives had been met. The new general timetable and budgetary plan are to be adopted at the next Council meeting in June, or in October 2010 at the latest.
It was also thought essential that the following conditions be met before the system becomes operational. The Milestone II test must be successfully carried out and the operating conditions must be fully met. The overall test for which there is provision in Article 55 of the Regulation must also be successfully carried out, and the safety of the network completely ensured.
Third question: why is it so urgent for these initiatives to be adopted? Although the conditions necessary in order to go ahead with the migration have not all been met, nor is a time foreseeable when that will be the case, the mandate that was granted to the Commission to develop the SIS II will expire again on 30 June 2010. We therefore have to amend the sunset clauses in the migration instruments adopted in 2008 in order to prevent them from expiring.
For my fourth and final question, what aspects of the proposals have I sought to amend? First, the insertion of a sunset clause, which the Commission had not proposed. We propose that it be set for 31 December 2013. Given the considerable delays, it is also essential that it be set out in the legal basis that the solution used, whatever it may be, must be based on the available technology, must follow a reasonable timetable and must be acceptable in terms of cost effectiveness.
The Global Programme Management Board must also be created, and its management of the SIS II formally integrated. I am absolutely convinced that if this body had existed from the start, we would have managed to be better coordinated, we would have known more, and we would have been more effective.
Finally, I consider it crucial that the migration process be submitted to parliamentary scrutiny. Parliament is not just responsible for the legal basis: as budgetary authority, it also ensures the supervision of actions financed by the Union budget. That is why I, alongside my fellow Member, Mr Alvaro, have tabled an amendment to place funds in reserve. I have also tabled an amendment alongside my fellow Members Mr Alvaro, Mrs Ludford, Mr Enciu and Mrs Hohlmeir to request an audit by the European Court of Auditors. I would like to thank everyone for being extremely cooperative."@en1
|
lpv:videoURI |
Named graphs describing this resource:
The resource appears as object in 2 triples